The first “pop-up” power plant to serve a Georgia data center has been ordered to stop construction and cited for a breach of state law by environmental officials, who say the company behind the project has built its power generators without a permit.

The Georgia Environmental Protection Division sent notices of violations last week to the power plant’s builder and the data center’s developer a day after a July 1 story by The Atlanta Journal-Constitution detailed how the companies had not received required permits before starting construction on dozens of gas engines.

The power plant in question is being built about 40 miles east of downtown Atlanta in Covington by the Houston-based firm VoltaGrid. Instead of plugging into the grid, the company plans to generate electricity for a data center under construction next door by developer Serverfarm.

VoltaGrid applied last year for an air permit from EPD that would allow it to run 33 natural gas-burning engines around-the-clock to power the data center. Serverfarm also applied for permission to install its own set of backup generators as an insurance policy for power outages.

Aerial view of off-grid generators being installed at a data center near Covington on Thursday, June 25, 2026. (Hyosub Shin/AJC)

Credit: Hyosub Shin/AJC

icon to expand image

Credit: Hyosub Shin/AJC

But EPD says both companies appear to have moved too fast.

On Thursday, the agency issued notices of violations to the companies alleging they broke state air pollution laws by installing power generators without a permit.

The VoltaGrid facility would be Georgia’s first “off-grid” power plant to provide electricity to a data center, but these sorts of power arrangements are becoming more common across the country. As data centers seek to meet their voracious power needs as quickly as possible, some see on-site generators as a path to avoid long wait times to connect to the power grid.

In Georgia, which has the authority to enforce parts of the federal Clean Air Act, air permits are also required before construction of any facility that can generate air pollution can begin.

EPD said it received information in late June indicating both VoltaGrid and Serverfarm had installed generators without a permit.

Kurt Widmann, a spokesperson for Serverfarm, said in a statement that, “Every action taken on this development project has been in careful consultation with the applicable authorities having jurisdiction.” Widmann added that Serverfarm, which has now received an air permit, has not operated any of its backup generators.

Representatives from VoltaGrid did not immediately respond to a request for comment on the alleged violation.

A sign is visible at a construction site where off-grid generators were being installed at a data center on Thursday, June 25, 2026, in Covington, Ga. (Hyosub Shin/AJC)

Credit: Hyosub Shin/AJC

icon to expand image

Credit: Hyosub Shin/AJC

The possible infractions were first flagged to EPD by the Southern Environmental Law Center on behalf of a pair of nonprofits, Sustainable Newton and the Altamaha Riverkeeper. The day before EPD issued the notices of violations, the AJC also published a story and photos documenting the apparent unpermitted construction.

Georgia environmental regulators have ordered VoltaGrid to immediately stop building their power plant, and asked both companies for more information, including an explanation of why they began construction without proper approval.

EPD said the information the companies provide “will be reviewed by the Division and used to determine if further enforcement action, including monetary penalties, is warranted.”

An aerial view of off-grid generators being installed at a data center in Covington on Thursday, June 25, 2026. (Hyosub Shin/AJC)

Credit: Hyosub Shin/AJC

icon to expand image

Credit: Hyosub Shin/AJC

Maurice Carter, the president and co-founder of Sustainable Newton, called the companies’ actions a wake-up call for Georgia, as it remains one of the hottest destinations in the country for new data centers.

“These specific incidents are a glaring reminder that we cannot rely solely on the good faith and trustworthiness of those seeking to do business here,” Carter said.

SELC senior attorney Patrick Anderson said he was pleased with EPD’s enforcement moves, but said he hopes the agency “takes further corrective actions that uphold the state’s permitting requirements and prevent future violations.”

PSC exploring an investigation

Georgia utility regulators, meanwhile, are considering an investigation into whether the data center developer’s plan to use a cluster of on-site generators to meet its power needs is allowed under state rules.

While most customers are assigned an electric utility to serve them based on where they’re located, certain large users get a one-time chance to choose their power provider.

It’s not clear exactly how much power Serverfarm will use, but the VoltaGrid power plant next door will have a maximum output of 90 megawatts, enough to power at least 36,000 homes. That’s well above the state’s “customer choice” threshold of 0.9 megawatts.

But during PSC committee meetings last week, Commissioner Peter Hubbard questioned whether the companies’ pop-up power plant is allowed under state law.

Citing the AJC’s reporting on the facilities’ rapid construction, Hubbard said he believes the power facility may violate the Georgia Territorial Electric Service Act, a 1973 law that divvied up the state’s land to different electricity providers. Hubbard asked the agency staff to explore a potential investigation into the matter.

Neither VoltaGrid nor Serverfarm responded to a request for comment on the potential PSC inquiry.

About the Author

Keep Reading

A view of the Sam Nunn federal building in Atlanta on Tuesday, June 3, 2025. (Arvin Temkar/AJC)

Credit: arvin.temkar@ajc.com

Featured

Aerial view of off-grid generators being installed, with the data center in the background, on Thursday, June 25, 2026, in Covington. A data center near Social Circle plans to get its primary power supply from a set of off-grid generators, the first setup of its kind in Georgia. But the company behind the power project is already installing its equipment, despite never obtaining proper permits from the state, a move environmental advocates say raises serious questions about oversight of data centers cropping up across Georgia. (Hyosub Shin/AJC)

Credit: Hyosub Shin/AJC